RECENT
PROJECTS
NSG has in the first two quarters of 2001 implemented three complex
WMS networks in Georgia, Florida and Ohio. The sites consisted of two
new distribution facilities, one existing warehouse and totaled 3.9
million square feet of property. Each project consisted of approximately:
- 1,500
sq. ft. of computer room with Liebert AC and UPS
- 250 kW
Kohler Diesel back-up power generation
- 45 Norand/Intermec
RF access points
- Average
of 10 telecommunication closets with conditioned power and 480 volt
emergency power back-up capabilities
- 500 data
user PC's, scanner and terminal nodes
- Total
network system implementation with Cisco hardware
- 200 speaker
Bogen zoned paging system
- 10 Pick-to-Light
controller network locations with conditioned power
- 2 conveyor
controller connections with conditioned power
- 400 user
voice infrastructure including pay telephone locations
- Time and
attendance Ethernet locations
STAY